2009 / 2010 Redevelopment Works

The Camping and Caravanning Club has begun network redevelopment in earnest starting Winter 2009 and carrying over into 2010 as part of a five year plan to position its site network amongst the best in the country by 2015.

Lauder Camping and Caravanning Club SiteThe majority of the work, which will include improvements to hard-standings, electric hook-ups, road surfaces, amenity blocks and staff facilities to name but a few, will be undertaken during the winter with minimal disruption being caused during the summer season.

Works carried out over winter 09/10:

  • Cannock Chase - Electrical and  hook-up upgrade and installation of 9 hard standings
  • Crowden - Electrical upgrade
  • Hayfield - Electrical upgrade
  • Oban - Resurfacing of site roads
  • Sandringham - Refurbish sewage treatment Bio-zones
  • Scone - Installation of 11 Caravan Holiday Home bases
  • Tarland - Electrical upgrade and installation of 6 Caravan Holiday Home bases
  • Winchcombe - Complete refurbishment of Amenity Block and Recreation Room, installation of site barrier and staff facilities
  • Windermere - Resurfacing of site roads

Hayfield Camping and Caravanning Club Site


2010 planned works already complete:

Additional works carried out this season so far:

Theobalds Park Camping and Caravanning Club SiteAdditional work scheduled for 2010

  • Crowborough - Construct caravan storage area, adapt 25 hard standings and construct 16 new hard standings
  • Dunstan Hill - Construct 15 new hard standings. Install underground gas tank
  • Glencoe - Installation of new land drainage to tenting area and widening of entrance road
  • Inverewe - Construct 11 hard standings & motor home service point
  • Kelvedon Hatch - Construct 17 hard standings
  • Moffat - Tarmac existing site roads and create new roads. Tarmac pathways around amenity block. Convert 10 hard standings to Club standard and construct 13 new hard standings. Refurbishment of service areas. Construct a new caravan storage area
  • Sennen Cove - Electrical upgrade
  • Verwood - Electrical upgrade
  • Walton on Thames - Extension of caravan storage area and site roads. Construct 11 hard standings

Check this page regularly for the latest updates on the Club Sites.